JB Engineering Services LTD carried out the complete removal of two existing I.S machines electrical control and cable management.
On our return trip to Germersheim we installed the complete electrical systems for two, 12 section, Heye - International I.S speedline machines. We also carried out the installation of all related equipment such as servo rotor, servo feeder, servo shear, servo gob distributor, machine conveyor, transfer wheel, cross conveyor and lehr loader.
Bespoke design of all cable management both inside the main control room and on the machine floor level offers optimum performance and ultimate protection for years to come.
Scope, as follows:
- Removal of all old control panels and installation of new, complete with wire basket under false floor.
- Removal of all old cable containment for both machines and installation of new.
- Removal of all old cables related to feeder, I.S machine & transport areas and then install new free issue cables.
- Installation of new control room supplies and termination into each cabinet.
- Installation of earthing arrangement inside control room.
- Manufacture and installation of stainless stands for feeder and transport control stations.
- Installation of all remote control boxes, isolators and stop / start units.
- Manufacture and installation of ducting attachments.
- Termination of all cables for both machines, including control room and field.
- Support machine manufacturer with start-up and commissioning.
- Project & logistic management.