Covington, Atlanta I.S Machine Mechanism Removal, Repair & Replacement

JB Engineering Services carried out an I.S Machine Section Exchange and I.S Machine Mechanism Removal, Repair & Replacement.

Our skilled engineers carried out an 8 section box exchange and; replaced all pipework for compressed air, contant cushioning and Lincoln lubrication lines. In addition to this planned installation, we removed all blowhead and baffle mechanisms on the 8 section I.S machine.

All client objectives were completed on time within 14 days. Our engineers worked in a tough, humid and noisy environment over 12 hour days to ensure this project was completed properly with the additional job getting done too.

I.S Machine Section Exchange
I.S Machine Section Exchange

JB Engineering Services LTD scope as follows:

  • Prepare tool and specialised lifting equipment, carry out detailed assessment on our procedures and identify any potential hazards to consider and eliminate.
  • Unwrap new section boxes and materials, remove blowhead, baffle and takeout Mechanisms aswell as the 21 way valve block ready for transportation and fitting.
  • Isolation of L12 Machine disconnection of all air, electrical and fluid services.
  • Removal of the I.S Machine conveyor – to be overhauled and modified within the workshop.
  • Removal of the existing section boxes.
  • Cleaning and preparation of the existing machine.
  • Modifications and installations of new manifold to blow and blankside.
  • Controlled installation of new Section boxes.
  • Installation of Mechanisms to all sections.
  • The manufacture of all solid pipework to all sections for main air, pilot air, constant cushioning and Lincoln lubrication systems.
  • The installation of refurbished machine conveyor.
  • The reconnection of other air services for mould and conveyor cooling.
  • Cold start up of the I.S Machine and testing of operation.
  • Machine started in full production.